Capital Project Updates

This page is updated regularly to provide Parkland residents with timely and accurate information regarding on-going capital improvement projects. For additional information on any project, please contact the City Engineering Department at 954-757-4165.

construction
 
Page Updated 10/12/18

LIGHTING PROJECT  SCHEDULES:
All projects to be completed with LED fixtures

NOB HILL ROAD LIGHTING PROJECT
North of Heron Bay to W. Hillsboro Boulevard
W. Hillsboro Boulevard to Loxahatchee Road
FPL has begun pole installation. The project was delayed due to field pole relocation due to utility conflicts and to improve the aesthetics of the location of the pole. Work is scheduled to begin by the end of July with completion by early November.
 
UNIVERSITY DRIVE
Holmberg Road to Loxahatchee Road

FPL has commenced the installation of poles. The project was delayed due to field pole relocation due to utility conflicts and to improve the aesthetics of the location of the pole. Work is scheduled for completion by early November.

W. HILLSBORO BOULEVARD  
Nob Hill Road to University Drive
Lighting construction is expected to begin in February of 2019 with completion of construction by April 2019.

TRAILS END BOULEVARD
Nob Hill Road to University Drive
Lighting construction start date TBD.

PINE ISLAND ROAD
NW 66th Drive to Nob Hill Road
Lighting construction start date TBD.

       ____________________________________________________
 
 
LIBRARY EXPANSION PROJECT
The City of Parkland Library is currently housed in a 13,200 square foot facility at the Parkland Municipal Complex.  Work is underway to redesign the facility by adding a wing to the existing building.  The wing will add approximately 7,000 square feet to the program space.  This addition  will provide a separate space for children and families and a multi-purpose program area.  The City Commission awarded the design to the architectural firm of Williamson Dacar Associates, Inc.  Commission awarded the construction to Di Pompeo Construction Corp. with construction anticipated to begin in October.
       
LOXAHATCHEE ROAD IMPROVEMENTS
The reconstruction of Loxahatchee Road (Lox) is a large-scale collaboration between the City of Parkland (City), Broward County, the Broward Metropolitan Planning Organization, and the Florida Department of Transportation (FDOT).  The project will span Lox from US 441/State Road 7 (SR 7) to the water conservation area.

This project will, in effect, be a complete makeover of the road through its entire span.  Travel lanes will be widened to 11', there will be bike lanes in both directions, a sidewalk along the south side of the road, and much of the roadway will have a landscaped median that will not only provide traffic calming, but will add a Parkland feel to the road.  Additionally, there will be street lights atop cement utility poles all the way from SR 7 to the west end of Lox.

The vision is to create a safe, bright aesthetically-pleasing passage from east to west in Parkland.  City staff is working with all involved agencies to ensure the project stays on track.  Originally funding was expected in fiscal year 2020-2021, but, at the City's prompting, it has been expedited for funding in 2019. 

FDOT has awarded the project design contract to Protean Design Group. Construction is anticipated to begin in late 2019/early 2020. The design is expected to be completed in the fall of 2019. A public hearing was held August 30, 2018.
  
FIRE STATION 42 ADDITION
This project involves the expansion of Fire Station 42 approximately 300 square feet for the purpose of adding two (2) additional bunks and a bathroom. The City Commission awarded the design to Keith & Associates at the January 31st Commission meeting. The concept has been submitted and approved. Project to be advertised in October 2018 and then awarded for construction in January 2019.

CITY HALL BUILDING DEPARTMENT EXPANSION                                                                            
This project involves the expansion of the existing building space for an additional 3,000 square feet. The expansion, once complete, will accommodate additional space for the Building Department in addition to space for the City's record retention files. Commission awarded the construction to Lynx Construction Management. Construction has commenced and is expected to be completed by the end of 2018. 

Contact Us

  1. Contact

    Jeanine Athias
    City Engineer

    6600 University Drive
    Parkland, FL 33067

    Ph: (954) 757-4184
    Fax: (954) 753-8838

    Hours


    Monday - Friday
    8:00 A.M. - 5:00 P.M.